Before you offer
From the City's records on this lot. Each item says what it means for a purchase and how to confirm it.
Not in these records
- Flooding history. Past basement flooding and insurance claims on this house are not published. Ask the seller directly and ask your insurer before you firm up the offer.
- Ownership, mortgages and easements. Title is not open data. Your lawyer searches title after the offer; ask for the survey and any easements before.
History of this lot
16 records on file: more than at 100% of Toronto houses (median 0).
- Zoning review25 108715 LPRCancelledJan 24, 2025 · 85 THE POND RD
- Building permit24 208059Closed
1 wall sign**PAPA JOHNS**
Sep 11, 2024 · 85 THE POND RD - Building permit24 202789Cancelled
1 wall sign**PAPA JOHNS**
Aug 23, 2024 · 85 THE POND RD - Building permit24 196482Cancelled
1 wall sign**PAPA JOHNS**
Aug 12, 2024 · 85 THE POND RD - Building permit24 166975Closed
INTERIOR ALTERATION FOR A PAPA JOHN'S PIZZA RESTAURANT, SCOPE OFWORK INCLUDES INTERIOR PARTITIONING, DISTRIBUTION OF THE AC SYSTEMKITCHEN EXHAUST & MAKE UP AIR SYSTEMS AND PLUMBING WORKS.
Jun 27, 2024 · 85 THE POND RD - Zoning review23 180392 LTOClosedJul 27, 2023 · 85 THE POND RD
- Building permit22 229154Closed
Plumbing - Proposal for interior alterations to existing retail space - UNIT R110
Jul 13, 2023 · 85 THE POND RD - Building permit23 160488Closed
The proposal contains two first party wall signs, both illuminated and displaying static copy, erected at the first storey of the building at above noted premises.Dimensions:Sign 1: 0.24m L x 5.94m W x 0.08m D at a height of 2.57m, on the north elevation.Sign 2: 0.24m L x 5.59m W x 0.08m D at a height of 2.57m, on the east elevation.****CHIPOTLE MEXICAN GRILL****
Jul 6, 2023 · 85 THE POND RD
Show 8 older records
- Building permit23 128461Closed
To erect and display one first party wall sign, displaying static copy, erected at the first storey on the east elevation of the building.Dimensions:0.66m L x 3.94m W x 0.08m D at a height of 2.82m.**INSOMNIA COOKIES LLC**
May 1, 2023 · 85 THE POND RD - Building permit23 106754Closed
new tenant improvement
Apr 3, 2023 · 85 THE POND RD - Building permit22 226129Closed
In conjunction with a student residence on the premises, the proposal to erect and display two signs in total. One electronic ground sign displaying electronic static copy. And one illuminated ground sign displaying static copy. Both signs already approved by variance # 22-155996**QUAD**
Nov 22, 2022 · 85 THE POND RD - Building permit22 142353Closed
Application for a permit to erect and display three ground signs,all non- illuminated.and displaying static copy.*****QUAD*****
Aug 16, 2022 · 85 THE POND RD - Zoning review22 155996 ZSVClosedJun 2, 2022 · 85 THE POND RD
- Building permit20 184518Closed
Conditional Permit - Proposal to construct a new eight storey student residence consisting of 17,387 square meters, 274 residential units, 681 square meters of grade-related retail. No Basement
Jun 29, 2021 · 85 THE POND RD - Building permit21 118871Approved
Combustible composite metal panel system, designated ALPOLIC/FR, an aluminium composite metal (ACM) panel system installed in limited areas on the exterior face of the building which exceeds 6 storeys, will provide the level of performance required by 3.1.5.5.(1) & (2) of the 2021 OBC
Feb 22, 2021 · 85 THE POND RD - Building permit20 171737Approved
This Alternative Solution proposes the installation of fire hose connections in the exit stairs at the main floor landings in lieu of hose stations in the corridors located within 5 m of the exits stairs. The inherent features of this design takes into consideration the provision of a safe staging area to commence firefighting with the 65 mm hose connections at the main floor landings in the exit stairs, rather than using fire hose connections on another floor level. The proposed approach is consistent with NBC Division B requirement for the standpipe system to meet NFPA 14, and eliminates the need to run hoses through the exit stair from the floor level below, and reduces the number of doors to the exit stair that may be propped open during firefighting operations.The inherent building features combined with the proposed design of the standpipe system will not adversely impact Fire Department operations and allows for consistent and unhindered access to hose connections. In addition, a safe staging area is provided for firefighters that is consistent with the performance level required by the OBC.This approach is applied in jurisdictions across Canada where the NBC is adopted or amended, and is also applied within federally regulated buildings across Canada including in Ontario. As such, responding fire departments have familiarity with the proposed arrangement without requiring building specific knowledge, specialized training, or specialized tactics.The proposed Alternative Solution therefore is considered to provide a performance level that is at least equal to the performance level provided by the requirements prescribed in OBC Division B Article 3.2.9.4 and as such is compliant with the Ontario Building Code as stated in Division A Clause 1.2.1.1.(1)(b).(See attached report)
Jul 23, 2020 · 85 THE POND RD
Check before you build
Zoning not in By-law 569-2013
Needs a closer lookThis lot is not covered by the citywide zoning by-law's map. It is probably still governed by a former municipal by-law, which this tool does not read yet.
Zoning By-law 569-2013
Lot facts
- Area
- 6,728 m²
- Frontage
- 82.1 m
- Depth
- 85.6 m
- Street
- Leitch Ave
- Corner lot
- Yes, also on The Pond Rd85.6 m along it
- Public lane
- None
- Max height
- —
- Max lot coverage
- —
Around this lot
- Minor variances approved
- —no decisions on file
- Garden suite permits
- 0
- Laneway suite permits
- 0
- Multiplex permits
- 0
- Development applications
- 1
Within 300 m, last 10 years. 0 suite and multiplex permits: no more than at most Toronto houses (median 3). 0 variance decisions: no more than at most Toronto houses (median 19).
Recent variance decisions in the same zone
- Minor varianceApproved
To maintain the existing lodging house which will contain a total of 8 rooms and to construct a rear yard platform.
14 BOAKE ST · May 28, 2026 · 328 m away - Minor varianceApproved
To alter the existing building to contain a total of 7 dwelling rooms. The existing dwelling unit and secondary suite will be maintained.
27 MANSUR TER · Feb 6, 2025 · 458 m away - Minor varianceApproved
To construct two new 8-storey student housing buildings.
4700 KEELE ST · Mar 7, 2024 · 443 m away - Minor varianceApproved
To permit an Crisis Care Shelter.
26 MANSUR TER · Jul 28, 2022 · 487 m away - Minor varianceApproved
To relocate the Regenesis Community Bike Centre from Building C1 to Building C2.
4300 KEELE ST · Feb 8, 2018 · 360 m away
Latest activity nearby
- Building permit
Proposal for interior alteration of existing academic and office spaces for a new School of Medicine which includes Student Academic and Study Spaces, Clinical Simulation Rooms, and Administration and Office Suites.
88 THE POND RD · Nov 16, 2026 · 170 m away - Building permit
Proposal for below grade stair.
90 LEITCH AVE · Apr 8, 2026 · 182 m away - Building permit
Proposal for interior alterations, fit-out for new restaurant
105 THE POND RD · Oct 7, 2025 · 249 m away - Building permit
Part Permit - Proposal to construct a new 8-storey Student Residence consisting of 17,736 square metres, 335 residential units. See also 23-238032 WET 07 MV & 24-124627 WET 07 PAC
100 HAYNES AVE · Mar 20, 2025 · 162 m away - Building permit
Part Permit - Proposal to construct a new 8-storey Student Residence (Building C7) consisting of 13,964 square metres, 251 residential units. See also 23-138032 WET 07 MV & 24-124627 WET 07 PAC
95 HAYNES AVE · Mar 20, 2025 · 107 m away - Zoning review
Cancelled
85 THE POND RD · Jan 24, 2025 · 31 m away - Building permit
Combustible composite metal panel system, designated Alpolic/fr, an aluminum composite metal (ACM) panel system installed in limited areas on the exterior face of the building which exceeds 6 storeys will provide the level of performance required by 3.1.5.5.(1) & (2) of the 2012 OBC.
100 HAYNES AVE · Dec 27, 2024 · 162 m away - Building permit
Combustible composite metal panel system, designated Alpolic/fr, an aluminum composite metal (ACM) panel system installed in limited areas on the exterior face of the building which exceeds 6 storeys will provide the level of performance required by 3.1.5.5.(1) & (2) of the 2012 OBC.
95 HAYNES AVE · Dec 27, 2024 · 107 m away - Building permit
This Alternative Solution proposes the installation of fire hose connections in the exit stairs at the main floor landing in lieu of hose stations in the corridors located within 5 m of the exits stairs. The inherent features of this design takes into consideration the provision of a safe staging area to commence firefighting with the 65 mm hose connections at the intermediate floor landings in the exit stairs, rather than using fire hose connections on another floor level. The proposed approach is consistent with NBC Division B requirement for the standpipe system to meet NFPA 14, and eliminates the need to run hoses through the exit stair from the floor level below, and reduces the number of doors to the exit stair that may be propped open during firefighting operations.The inherent building features combined with the proposed design of the standpipe system will not adversely impact Fire Department operations and allows for consistent and unhindered access to hose connections. In addition, a safe staging area is provided for firefighters that is consistent with the performance level required by the OBC.This approach is applied in jurisdictions across Canada where the NBC is adopted or amended, and is also applied within federally regulated buildings across Canada including in Ontario. As such, responding fire departments have familiarity with the proposed arrangement without requiring building specific knowledge, specialized training, or specialized tactics.The proposed Alternative Solution therefore is considered to provide a performance level that is at least equal to the performance level provided by the requirements prescribed in OBC Division B Article 3.2.9.4 and as such is compliant with the Ontario Building Code as stated in Division A Clause 1.2.1.1.(1)(b).(See attached report)
95 HAYNES AVE · Dec 10, 2024 · 107 m away - Building permit
This Alternative Solution proposes the installation of fire hose connections in the exit stairs at the main floor landings in lieu of hose stations in the corridors located within 5 m of the exits stairs. The inherent features of this design takes into consideration the provision of a safe staging area to commence firefighting with the 65 mm hose connections at the intermediate floor landings in the exit stairs, rather than using fire hose connections on another floor level. The proposed approach is consistent with NBC Division B requirement for the standpipe system to meet NFPA 14, and eliminates the need to run hoses through the exit stair from the floor level below, and reduces the number of doors to the exit stair that may be propped open during firefighting operations.The inherent building features combined with the proposed design of the standpipe system will not adversely impact Fire Department operations and allows for consistent and unhindered access to hose connections. In addition, a safe staging area is provided for firefighters that is consistent with the performance level required by the OBC. This approach is applied in jurisdictions across Canada where the NBC is adopted or amended, and is also applied within federally regulated buildings across Canada including in Ontario. As such, responding fire departments have familiarity with the proposed arrangement without requiring building specific knowledge, specialized training, or specialized tactics.The proposed Alternative Solution therefore is considered to provide a performance level that is at least equal to the performance level provided by the requirements prescribed in OBC Division B Article 3.2.9.4 and as such is compliant with the Ontario Building Code as stated in Division A Clause 1.2.1.1.(1)(b).(See attached report)
100 HAYNES AVE · Dec 10, 2024 · 162 m away
Neighbourhood: York University Heights
About the area around the lot, not the lot itself.
- Nearest station
- Finch West Station14 min walk
- Nearest TTC stop
- The Pond Rd at Ian MacDonald Blvd1 min walk
- Nearest cycling route
- The Pond RdSharrows - Wayfinding, 1 min walk
- Nearest traffic count
- 8,979 vehicles in 14 hThe Pond Rd / Ian Macdonald Blvd / Leitch Ave, 70 m away, Mar 7, 2024
- Serious collisions within 500 m
- 12021–2026, killed or seriously injured: 0 fatal, 1 with pedestrians, 0 with cyclists
- Parks
- Jack Evelyn Wiggins Park5 min walk
- Four Winds Allotment Gardens9 min walk
- Fred Young Park10 min walk
Schools within 1 km
- SENECA COLLEGE (SENECA AT YORK CAMPUS) College 2 min walk
- YORK U - KEELE CAMPUS University 7 min walk
- JAMES CARDINAL MCGUIGAN CATHOLIC HIGH SCHOOL English Separate 14 min walk
Being near a school does not mean the lot is in its catchment; check with the board.
2021 Census
| Figure | York University Heights | Median neighbourhood |
|---|---|---|
| Median household income (2020) | $76,000 | $84,500 |
| Households that own their home | 47% | 54% |
| Population (2021) | 28,255 | 16,813 |
| Homes built in 1960 or before | 14% | 29% |
| Homes needing major repairs | 8% | 7% |
Statistics Canada 2021 Census, 25% sample, by City of Toronto neighbourhood.
Police-reported crime, 2025
| Per 100,000 people | York University Heights | City median |
|---|---|---|
| Assault | 1274.1 | 636.3 |
| Robbery | 128 | 69.5 |
| Shootings | 11.9 | 10.5 |
| Auto theft | 634.1 | 192.6 |
| Theft over $5,000 | 178.6 | 46.1 |
| Break and enter | 375.1 | 172.8 |
| Theft from vehicles | 312.6 | 188.1 |
Neighbourhood totals from the Toronto Police Service. Rates are per resident, so areas with many visitors and few residents read high.