Open space · ON (x17)61.1 × 463.5 m24,920 m²on Commissioners Stcorner, also on Leslie St

Not a home

Leslie Street Maintenance Yard

The City of Toronto's real estate inventory lists Leslie Street Maintenance Yard here, on City land in City use. It is not a home for sale, so the house checks and the pre-offer report do not apply.

Looking at a house nearby? What this means for you

  • Utility or City worksTrucks and work noise at times.
  • Permits or applications open on this parcelRecent records on this lot: 25 203571 (Proposed interior alterations to the existing building to install a new blower and filt..., 2025); 23 208049 (PROPOSED: CONSTRUCTION OF THE IPS LOW VOLTAGE SUBSTATION WHICH HOUSES THE 4160V TO 600V..., 2025); 25 153855 (Drain - Proposal to construct a fenced concrete slab with a crawl space for the new sub..., 2025); and 6 more. Larger work can mean noise and trucks next door; read what each one is for.
N50 m
61.1 m frontage463.5 m deep

Before you offer

From the City's records on this lot. Each item says what it means for a purchase and how to confirm it.

  • TRCA regulated area (99% of lot)

    Needs a closer look

    Part of the lot is near a valley, floodplain, shoreline or wetland. Work there needs a TRCA permit and may be restricted.

    What it means. Additions, pools and new buildings in the regulated part need a TRCA permit and may be refused. Ask your insurer about flood coverage.

    How to confirm. A TRCA property inquiry letter says which policies apply ($385, at least two weeks). Details

    Ontario Regulation 41/24, TRCA Regulation Limit
  • 12 building permits open, the oldest since 2004

    Needs a closer look

    Still open in the City's records: 21 209440 (Z BUILDING - Proposal to reinforce Boiler Room Floor and Loading Dock Area, including r..., 2022, status Permit Issued); 20 228256 (Proposed installation of a new rooftop solar Photovoltic system at (existing) D-Buildin..., 2021, status Permit Issued); 19 140271 (Revision 01 - shifted floor drains, vent risers and SAN lineProposal to excavate for sc..., 2019, status Revision Issued); and 9 more.

    What it means. An open permit can mean work that was never finished or never passed final inspection. After closing, finishing it or closing the file can fall to you.

    How to confirm. Ask the seller for the final inspection records. A Property Information Report from Toronto Building lists open permits, inspections and outstanding orders ($214.79, about five business days). Details

    City of Toronto, Building Permits (active, cleared since 2017, cleared 2000-2016)
  • Natural Heritage System (19% of lot)

    Good to know

    Part of the lot is in the Natural Heritage System shown on Official Plan Map 9.

    What it means. New buildings or additions in that part need a natural heritage impact study.

    How to confirm. City Planning confirms the policies that apply. Details

    City of Toronto Official Plan, Map 9
  • Work or applications in progress

    Good to know

    Recent records on this lot: 25 203571 (Proposed interior alterations to the existing building to install a new blower and filt..., 2025); 23 208049 (PROPOSED: CONSTRUCTION OF THE IPS LOW VOLTAGE SUBSTATION WHICH HOUSES THE 4160V TO 600V..., 2025); 25 153855 (Drain - Proposal to construct a fenced concrete slab with a crawl space for the new sub..., 2025); and 6 more.

    What it means. The owner has planned or started work. Ask what it covers, whether it will be finished before closing, and who pays for what is left.

    How to confirm. Application details and decisions are in the City's Application Information Centre. A Property Information Report from Toronto Building lists open permits, inspections and outstanding orders ($214.79, about five business days). Details

    City of Toronto, Building Permits (active, cleared since 2017, cleared 2000-2016); City of Toronto, Committee of Adjustment applications (2001 onwards); City of Toronto, Development Applications
  • 2 Committee of Adjustment files on this lot

    Good to know

    2 approved. A1071/24TEY (To permit three one-storey prefabricated buildings (Buildings 1, 2, and 3), on this site, 2025); A0573/09TEY (To construct a two-storey building to be used as a biogas cogeneration facility, 2010).

    What it means. Approved variances and consents stay with the property, including any conditions in the decision. They allow what was approved, not more.

    How to confirm. Decisions are in the Application Information Centre; older files are available from the Committee of Adjustment office. Details

    City of Toronto, Committee of Adjustment applications (2001 onwards)

Not in these records

  • Flooding history. Past basement flooding and insurance claims on this house are not published. Ask the seller directly and ask your insurer before you firm up the offer.
  • Ownership, mortgages and easements. Title is not open data. Your lawyer searches title after the offer; ask for the survey and any easements before.

History of this lot

77 records on file: more than at 100% of Toronto houses (median 0).

  • Building permit25 203571Inspection

    Proposed interior alterations to the existing building to install a new blower and filter room equipment.

    Oct 1, 2025 · 9 LESLIE ST
  • Building permit23 208049Permit Issuednew building

    PROPOSED: CONSTRUCTION OF THE IPS LOW VOLTAGE SUBSTATION WHICH HOUSES THE 4160V TO 600V TRANSFORMERS

    Sep 15, 2025 · 9 LESLIE ST
  • Building permit25 153855Permit Issued

    Drain - Proposal to construct a fenced concrete slab with a crawl space for the new substation. The structural elements include concrete foundations, beams, columns, slab and heavy duty fence and associated steel frames. - - Grading and drainage adjustments, including the removal of the existing catch basin, installation of sub-drains, and a new catch basin. - Replacement of concrete curb and installation of a new concrete pad to facilitate access to the new substation.

    Aug 5, 2025 · 9 LESLIE ST
  • Building permit25 124691Permit Issued

    Proposal for Digester Control Building- Electrical Room: fo replacement of two existing chillers serving process cooling equipment (Not Related to Building HVAC). - Addition of a new split system heat pump to the Electrical Room to provide supplementary cooling to the room- Grading and drainage adjustments, including the removal of the existing catch basin, installation of sub-drains, and a new catch basin. Replacement of concrete curb and installation of a new concrete pad to facilitate access to the new substation

    Jun 10, 2025 · 9 LESLIE ST
  • Building permit25 124430Permit Issued

    Replacement of an existing rooftop chiller with two (2) new rooftop units, replacement of existing recirculation pumpsProposed addition of a new air handling unit (same capacity) to replace an existing AHU serving the office area. Integrating these units into Building Automation System (BAS)Removal of a decommissioned chiller

    Jun 4, 2025 · 9 LESLIE ST
  • Building permit25 126286Permit Issued

    Proposal for Plant Water Pumping Station - Replacement of two existing rooftop condensers & associated compressors with two (2) new units,Proposal for the replacement of two existing Air Handling Units with new to serve the Electrical Room Integrating these units into Building Automation System (BAS). Replacing air registers with new & installation of two new fire dampers on existing ductwork

    May 1, 2025 · 9 LESLIE ST
  • Building permit24 149613Inspectionnew building

    Proposal to legalize existing multiple accessory buildings (temporary prefabricated structures) on the lot

    Apr 10, 2025 · 7 LESLIE ST
  • Minor varianceA1071/24TEYApproved

    To permit three one-storey prefabricated buildings (Buildings 1, 2, and 3), on this site.

    Mar 5, 2025 · 7 LESLIE ST
Show 69 older records
  • Building permit24 254383Permit Issued

    Proposal for Treatment Plant Elevator Modernization, New power and lighting,Fire Alarm Systems and CCTV.

    Feb 27, 2025 · 9 LESLIE ST
  • Zoning review25 112997 ZAPClosed
    Feb 5, 2025 · 9 LESLIE ST
  • Building permit24 241408Permit Issued

    Proposed interior alterations including structural repairs, electrical upgrades and modifications to the process piping system and HVAC system upgrades.

    Feb 4, 2025 · 9 LESLIE ST
  • Building permit24 243029Cancelled

    Proposing the temporary use of two trailers in the designated trailer parking area to serve as an office and a laboratory. One trailer will function as the office, while the other will be utilized as the lab. This arrangement will remain in place until the building renovations are completed, ensuring that employees can continue their work without interruption.Proposing the temporary use of two trailers in the designated trailer parking area to serve as an office and a laboratory. One trailer will function as the office, while the other will be utilized as the lab. This arrangement will remain in place until the building renovations are completed, ensuring that employees can continue their work without interruption.

    Nov 25, 2024 · 9 LESLIE ST
  • Zoning review24 203649 ZAPApplication On Hold
    Aug 26, 2024 · 9 LESLIE ST
  • Zoning review23 231196 PSPClosed
    Jan 8, 2024 · 7 LESLIE ST
  • Development application23 231196 STE 14 SAClosed

    A Site Plan Control application to permit a new integrated pumping station as part of the existing Ashbridges Bay Water Treatment Plant which is to consist of four new buildings including a pump house, building screen, generator building, and IPS substation. The pump house is proposed to be two-storeys (22m) in height and will contain 1,375 square metres of GFA.

    Nov 29, 2023 · 7 LESLIE ST · City file
  • Building permit23 208322Cancelled

    HVAC - PROPOSED: CONSTRUCTION OF THE SEPTAGE AND TRUCK UNLOADING FACILITY STRUCTURE CONSISTING. SCOPE OF WORK ALSO INCLUDE ARCHITECTURAL FINISHINGS (e.g., ROLL-UP DOOR) AND OTHER COMPONENTS.

    Sep 28, 2023 · 9 LESLIE ST
  • Building permit23 208261Cancelled

    Drain - PROPOSED: CONSTRUCTION OF THE SCREEN BUILDING FACILITY STRUCTURE INCLUDING THE OPERATING FLOOR, SECOND FLOOR, AND ROOF. SCOPE OF WORK INCLUDES: (1) INTERNAL STRUCTURAL WORK WITHIN SHAFTS BENEATH SCREEN BUILDING, AND (2) ARCHITECTURAL FINISHINGS AND HARDWARE.

    Sep 28, 2023 · 9 LESLIE ST
  • Building permit23 208063Cancelled

    Drain - PROPOSED: CONSTRUCTION OF THE PUMP HOUSE BUILDING FACILITY STRUCTURE INCLUDING DEEP SHAFTS, OPERATING FLOOR, SECOND FLOOR, ADMINISTRATIVE FLOOR AND ROOF. SCOPE OF WORK ALSO COVERS ARCHITECTURAL FINISHING AND HARDWARE.

    Sep 27, 2023 · 9 LESLIE ST
  • Building permit23 207984Cancelled

    Drain - PROPOSED: CONSTRUCTION OF THE IPS SUBSTATION FACILITY STRUCTURE CONSISTING OF A LOWER LEVEL FLOOR HOUSING THE EAST AND WEST ELECTRICAL VAULTS, AND AN OPERATING LEVEL FLOOR HOUSING THE EAST AND WEST SWITCHGEAR ROOMS, PLC AND BATTERY ROOMS, AND TRANSFORMER BAYS. SCOPE OF WORK ALSO INCLUDE ARCHITECTURAL FINISHING AND HARDWARE.

    Sep 27, 2023 · 9 LESLIE ST
  • Building permit23 207931Cancelled

    Drain - PROPOSED: CONSTRUCTION OF A NEW 2-STOREY BUILDING TO STORE FIVE (5) NEW EMERGENCY GENERATORS TO MAINTAIN OPERATIONS OF BUILDING SERVICE EQUIPMENT AT THE ASHBRIDGES BAY WATER TREATMENT FACILITY. THE BUILDING WILL ALSO CONSIST OF A BASEMENT LEVEL ELECTRICAL ROOM.

    Sep 27, 2023 · 9 LESLIE ST
  • Building permit23 153052Closed

    REPLACEMENT OF FIRE ALARM CONTROL PANEL AND DEVICES

    Jun 22, 2023 · 9 LESLIE ST
  • Zoning review23 121575 ZAPClosed
    Mar 9, 2023 · 9 LESLIE ST
  • Building permit22 116802Cancelled

    Proposal to replace Air handling unit (1460) serving the lunch room and exhaust fan (1461),and make miscellaneous piping, valving, and BAS changes as noted on the contract drawings.

    Apr 8, 2022 · 9 LESLIE ST
  • Building permit21 209440Permit Issued

    Z BUILDING - Proposal to reinforce Boiler Room Floor and Loading Dock Area, including removing and replacing fireproofing, removal of process boilers and related systems, closing exterior wall where steam boiler breeching pipe exited the building. Convenience address is 9 Leslie St.

    Feb 2, 2022 · 7 LESLIE ST
  • Building permit20 228256Permit Issued

    Proposed installation of a new rooftop solar Photovoltic system at (existing) D-Building at the Plant. New rooftop access platform, guardrail and building substation extension. PV racking system details will be provided by April 2021 as a shop drawing from the Contractor.

    Oct 15, 2021 · 9 LESLIE ST
  • Zoning review21 178668 POZClosed
    Jul 30, 2021 · 7 LESLIE ST
  • Development application21 178668 STE 14 OZClosed

    City-initiated Official Plan and Zoning By-law amendments to apply appropriate land use and zoning permissions to newly created landform south of the Ashbridges Bay Treatment Plant consistent with approved Environmental Assessment. Newly created lands will accommodate public utility infrastructure that will increase water quality and enhance shoreline stabilization and create additional park land and public access along the shoreline south of the plant.

    Jul 2, 2021 · 7 LESLIE ST · City file
  • Building permit21 145184Closed

    Ashbridges Bay Treatment Plant - Minor alterations and renovation to existing washrooms in Z Building to meet AODA requirements.

    May 11, 2021 · 9 LESLIE ST
  • Zoning review21 150148 ZPRClosed
    May 4, 2021 · 9 LESLIE ST
  • Zoning review21 150147 ZPRClosed
    May 4, 2021 · 9 LESLIE ST
  • Zoning review21 150143 ZPRClosed
    May 4, 2021 · 9 LESLIE ST
  • Zoning review21 150146 ZPRClosed
    May 4, 2021 · 9 LESLIE ST
  • Building permit20 219583Closed

    To modify original service platform No. 2 in screen building into five small platforms complete with access ladder - Ashbridges Bay Treatment Plant

    Dec 17, 2020 · 7 LESLIE ST
  • Building permit19 162719Cancelled

    Proposal for new construction in the 4 following areas: Area 1 = De-watering Building - replacement of existing roofing and new platformArea 2 = Polymer Facility - extension of existing mezzanine, replace roof and roofing systemArea 3 = Polymer Unloading Bay - 2 storey office addition to Pelletizer building and replace roofing Area 4 = Sludge equalization tanks - addition of new electrical room above tanks.

    Jun 23, 2020 · 7 LESLIE ST
  • Building permit12 174701Closed

    Rev01: changes as per drawings

    Feb 11, 2020 · 9 LESLIE ST
  • Building permit19 124789Closed

    REV01: Revision to permit 19-124789 BLD as per bubbled area.Proposal to construct a double wide trailer to be used as offices and training rooms at existing water treatment plant - "Ashbridges Bay Treatment Plant"Convenience address is 9 Leslie St.

    Oct 1, 2019 · 7 LESLIE ST
  • Building permit19 140271Revision Issued

    Revision 01 - shifted floor drains, vent risers and SAN lineProposal to excavate for screen building, substructure construction, shafts and tunneling. This application specifically refers to Screen Building plumbing drains in ground floor slab - "Ashbridges Bay Treatment Plant". Convenience addresses include 7 and 9 Leslie St.

    Aug 16, 2019 · 7 LESLIE ST
  • Building permit18 186307Permit Issued

    Relocate existing 250 mm diameter domestic water service to Ashbridges Bay Treatment Plant; Watermain is to be lowered to a depth of 1.8m.

    Jul 16, 2018 · 9 LESLIE ST
  • Zoning review18 190657 ZPRClosed
    Jul 9, 2018 · 7 LESLIE ST
  • Building permit17 268482Closed

    HVAC - Proposed upgrade and replacement of sludge feed, mixing, recirculation and transfer systems, gas systems and ancilliary electrical, instrumentation and control systems of Digesters 9-12. Installation of new structural steel roof systems, structural modifications to the control building and installation of new architectural systems.

    May 11, 2018 · 9 LESLIE ST
  • Building permit18 145415Inspection

    Proposal to relocate existing fire main to 2m below existing road surface. Convenience address is 9 Leslie St.

    Apr 26, 2018 · 7 LESLIE ST
  • Building permit17 230608Closed

    Proposal to do interior alterations to existing lunchroom

    Sep 29, 2017 · 9 LESLIE ST
  • Building permit17 148370Inspection

    Proposal to create a platform for maintenance access for crane repair

    Jun 2, 2017 · 7 LESLIE ST
  • Building permit17 103675Inspection

    Replace existing fire alarm control panel and annunciator

    Jan 18, 2017 · 9 LESLIE ST
  • Building permit16 129821Closed

    HVAC - Proposal for interrior alterations to tunnels "D" "F", "Ashbridges Bay Treatment Plant"

    Jul 12, 2016 · 7 LESLIE ST
  • Building permit16 129650Closednew building

    Proposal to install 1 new pre fabricated modular control room to be located on the site of an existing industrial building. Convenience address is 9 Leslie St.

    Jun 20, 2016 · 7 LESLIE ST
  • Building permit16 144798Closed

    Proposal to install a complete hot water secondary loop and glycol tertiary loop in Z-Building basement feed from the existing plant wide primary loop

    May 17, 2016 · 9 LESLIE ST
  • Building permit16 115886Cancelled

    Proposal to install 1 new pre fabricated modular control room to be located on the site of an existing industrial building. Convenience address is 9 Leslie St.

    Feb 11, 2016 · 7 LESLIE ST
  • Building permit15 230065Closed

    Proposal to install (1) backflow prevention device and expansion tank.

    Oct 27, 2015 · 7 LESLIE ST
  • Building permit15 228091Closed

    To install a back flow prevention device

    Oct 27, 2015 · 7 LESLIE ST
  • Zoning review15 185006 ZPRClosed
    Jul 3, 2015 · 9 LESLIE ST
  • Building permit15 141170Closed

    Interior Alterations addition of a new washroom on 5th floor

    Jun 17, 2015 · 9 LESLIE ST
  • Building permit14 268533Closednew building

    Proposal to construct a new Biofilter building and Biofilter control room at Ashbridges Bay.

    Jun 17, 2015 · 9 LESLIE ST
  • Building permit14 268528Closed

    Proposal for interior alterations to the truck loading bay serving Ashbridge's bay sewage treatment plant to construct a 2nd storey mezzanine in the existing industrial building.

    Jun 17, 2015 · 9 LESLIE ST
  • Building permit14 267351Closednew building

    Proposal to construct a new waste gas burning facility at Ashbridges bay.

    Mar 6, 2015 · 9 LESLIE ST
  • Building permit14 254945Permit Issued

    Standalone plumbing permit for upgrades to fixtures and subsequent pipes in an existing 2nd floor lunchroom - Toronto Water Ashbridges Bay Treatment Plant.

    Dec 22, 2014 · 9 LESLIE ST
  • Zoning review09 166006 PSPClosed
    Sep 16, 2014 · 7 LESLIE ST
  • Building permit14 138325Inspection

    Interior alterations to the existing water and sewage pumping station owned by Toronto Water. Alterations will be made to the existing machine control centre and foundation for 2nd prefab MCC module.

    May 27, 2014 · 9 LESLIE ST
  • Building permit14 140845Inspection

    Proposal for interior alterations to structuraly reinforce basement ceiling in existing Toronto Water Ashbridges Bay Treatment Plant.

    May 2, 2014 · 9 LESLIE ST
  • Building permit13 270776Closed

    HVAC - Proposal for interior alterations to washrooms at 9 Leslie St in the Training Center. Proposal includes HVAC and PLB.

    Jan 13, 2014 · 7 LESLIE ST
  • Building permit13 210112Closed

    Proposal to construct new 1hr fire rated screen assembly in control room with interior altearations for Toronto Water Ashbridges Bay Treatment Plant.

    Aug 7, 2013 · 9 LESLIE ST
  • Building permit13 120365Closed

    Proposal to install 3 Backflow Preventors in the Grit Building - "Ashbridges Bay Wastewater Treatment Plant"

    Mar 7, 2013 · 9 LESLIE ST
  • Building permit12 276494Closeddemolition

    Proposal to demo existing 1 sty storage building. See new BLD permit 11 274433.

    Nov 28, 2012 · 7 LESLIE ST
  • Building permit12 274433Closednew building

    Proposal to construct a new storage shed. City of Toronto Yard. See Site Plan Approval.

    Nov 28, 2012 · 7 LESLIE ST
  • Building permit12 174714Closeddemolition

    Proposal to remove portions of industrial building complex and associated underground channels for Toronto Water Services treatment plant (1240m2). This is considered a building alteration along with related construction permit 12-174701.

    Aug 21, 2012 · 9 LESLIE ST
  • Building permit12 197737Inspection

    This is for interior alterations to the ground floor of the "ASHBRIDGES BAY TREATMENT PLANT". This is for the creation of a new electrical room within the existing walls and work to the MCC rooms along with a new layout at a portion of the ground floor. This application is actually closer to 1313 Lake Shore Blvd E.

    Aug 3, 2012 · 9 LESLIE ST
  • Zoning review11 121836 PSPClosed
    Feb 8, 2011 · 7 LESLIE ST
  • Development application11 114995 STE 32 SAClosed

    Site Plan Approval to construct a new one-storey storage building (403 m2) in the same location as the existing storage building (to be demolished). The new building would continue to be operated by Transportation Services (City of Toronto).

    Jan 27, 2011 · 7 LESLIE ST
  • Zoning review10 293709 ZPRClosed
    Nov 9, 2010 · 7 LESLIE ST
  • Building permit10 177306Closed

    new sidewalk and alterations to exterior stairs

    Jun 28, 2010 · 9 LESLIE ST
  • Minor varianceA0573/09TEYApproved

    To construct a two-storey building to be used as a biogas cogeneration facility.

    Feb 10, 2010 · 7 LESLIE ST
  • Building permit08 193817Closed - Dormant

    Plumbing - Ashbridges Bay. Interior alterations to existing office/laboratory building.

    Sep 8, 2008 · 9 LESLIE ST
  • Building permit08 109969Closed

    Make interior alterations to washrooms.

    Mar 10, 2008 · 9 LESLIE ST
  • Zoning review08 114178 ZZCClosed
    Feb 25, 2008 · 7 LESLIE ST
  • Building permit04 149324Inspection

    HVAC - Refurbishing of digesters 1-12 at the Ashdridges Bay Treatment Plant. Refer to dwg #1001-2004-02-A002 for the design statement. - Multiple Projects

    Aug 16, 2004 · 7 LESLIE ST
  • Building permit03 195203Closed - Dormant

    HVAC - To make interior alterations to ground floor and mezzanine (office space)PRESENT USE: STORAGE YARD (METRO ROADS AND TRAFFIC)PROPOSED USE: SAME - Interior Alterations

    Feb 23, 2004 · 7 LESLIE ST
  • Building permit03 157163Closed - Dormant

    make structural roofing repairs on the existing salt domes and repairs to the front entrance.

    Jul 23, 2003 · 7 LESLIE ST

Check before you build

  • Site-specific exception 900.41.10(17)

    Needs a closer look

    2 site-specific rules apply to this lot. They can override the standard rules on this page.

    Zoning By-law 569-2013, Chapter 900
Exception 900.41.10(17)Applies

These parts of the exception apply to this lot's address.

  1. Rule A

    In addition to the uses listed in Clause 90.20.20.20, the following additional uses are permitted if they comply with the associated condition(s): (i) Take-out eating Establishment if the gross floor area does not exceed 500 square metres; and (ii) Eating Establishment if the gross floor area does not exceed 500 square metres and subject to the specific use regulations in Section 150.100; and (iii) Outdoor Patio if it is combined with an Eating Establishment or Take-out Eating Establishment use and is not used to provide entertainment such as performances, music and dancing

  2. Rule B

    Despite regulation 90.20.20.100(3) a retail store is not required to be associated with an agricultural use on the same lot .

By-law 569-2013, Chapter 900

Lot facts

Area
24,920 m²
Frontage
61.1 m
Depth
463.5 m
Street
Commissioners St
Corner lot
Yes, also on Leslie St463.5 m along it
Public lane
None
House footprint
563 m²roof up to 15 m
Back yard
125.7 mhouse to rear lot line
Side yards
9.4 m and 27.8 mhouse to side lot lines
Buildings on the lot
10house, garage, sheds
Max height
15 m
Max lot coverage
—

House and yards are measured from the City's 3D Massing footprints, which are for illustration; a survey gives the exact figures.

  • Central Waterfront Secondary Plan. A Secondary Plan sets more detailed land use, height and density policies for this area. Source
  • Zone ON (x17) (Open Space Natural). Chapter 90, section 90.20 of the by-law. Source

Around this lot

Minor variances approved
100%1 of 1 decisions
Garden suite permits
0
Laneway suite permits
0
Multiplex permits
0
Development applications
5

Within 300 m, last 10 years. 0 suite and multiplex permits: no more than at most Toronto houses (median 3). 1 variance decisions: no more than at most Toronto houses (median 19).

Recent variance decisions in the same zone

  • Minor varianceApproved

    To permit three one-storey prefabricated buildings (Buildings 1, 2, and 3), on this site.

    7 LESLIE ST · Mar 5, 2025 · 50 m away

Latest activity nearby

  • Building permit

    Proposal to upsize domestic cold water service.

    651 COMMISSIONERS ST · Oct 14, 2025 · 166 m away
  • Building permit

    Proposed interior alterations to the existing building to install a new blower and filter room equipment.

    9 LESLIE ST · Oct 1, 2025 · 67 m away
  • Building permitnew building

    PROPOSED: CONSTRUCTION OF THE IPS LOW VOLTAGE SUBSTATION WHICH HOUSES THE 4160V TO 600V TRANSFORMERS

    9 LESLIE ST · Sep 15, 2025 · 67 m away
  • Building permit

    Drain - Proposal to construct a fenced concrete slab with a crawl space for the new substation. The structural elements include concrete foundations, beams, columns, slab and heavy duty fence and associated steel frames. - - Grading and drainage adjustments, including the removal of the existing catch basin, installation of sub-drains, and a new catch basin. - Replacement of concrete curb and installation of a new concrete pad to facilitate access to the new substation.

    9 LESLIE ST · Aug 5, 2025 · 67 m away
  • Building permit

    Proposal for Digester Control Building- Electrical Room: fo replacement of two existing chillers serving process cooling equipment (Not Related to Building HVAC). - Addition of a new split system heat pump to the Electrical Room to provide supplementary cooling to the room- Grading and drainage adjustments, including the removal of the existing catch basin, installation of sub-drains, and a new catch basin. Replacement of concrete curb and installation of a new concrete pad to facilitate access to the new substation

    9 LESLIE ST · Jun 10, 2025 · 67 m away
  • Building permit

    Proposal for installation of a domestic premise isolation backflow preventer to replace an existing one that cannot be repaired.

    651 COMMISSIONERS ST · Jun 6, 2025 · 166 m away
  • Building permit

    Replacement of an existing rooftop chiller with two (2) new rooftop units, replacement of existing recirculation pumpsProposed addition of a new air handling unit (same capacity) to replace an existing AHU serving the office area. Integrating these units into Building Automation System (BAS)Removal of a decommissioned chiller

    9 LESLIE ST · Jun 4, 2025 · 67 m away
  • Building permit

    Proposal for Plant Water Pumping Station - Replacement of two existing rooftop condensers & associated compressors with two (2) new units,Proposal for the replacement of two existing Air Handling Units with new to serve the Electrical Room Integrating these units into Building Automation System (BAS). Replacing air registers with new & installation of two new fire dampers on existing ductwork

    9 LESLIE ST · May 1, 2025 · 67 m away
  • Building permitnew building

    Proposal to legalize existing multiple accessory buildings (temporary prefabricated structures) on the lot

    7 LESLIE ST · Apr 10, 2025 · 50 m away
  • Minor varianceApproved

    To permit three one-storey prefabricated buildings (Buildings 1, 2, and 3), on this site.

    7 LESLIE ST · Mar 5, 2025 · 50 m away

Neighbourhood: South Riverdale

About the area around the lot, not the lot itself.

Nearest station
Donlands Station49 min walk
Nearest TTC stop
Leslie St at Commissioners St3 min walk
Nearest cycling route
Martin Goodman / Waterfront TrlMulti-Use Trail, 1 min walk
Nearest traffic count
8,331 vehicles in 14 hLeslie St / Commissioners St / Martin Goodman Trl, 130 m away, Oct 6, 2026
Serious collisions within 500 m
12021–2026, killed or seriously injured: 0 fatal, 0 with pedestrians, 1 with cyclists
Parks
Leslie Lookout Park2 min walk
Leslie Street Allotment Gardens4 min walk
Tommy Thompson Park7 min walk

Schools within 1 km

  • BRUCE JR PUBLIC SCHOOL English Public 14 min walk

Being near a school does not mean the lot is in its catchment; check with the board.

2021 Census

FigureSouth RiverdaleMedian neighbourhood
Median household income (2020)$100,000$84,500
Households that own their home57%54%
Population (2021)27,81516,813
Homes built in 1960 or before52%29%
Homes needing major repairs7%7%

Statistics Canada 2021 Census, 25% sample, by City of Toronto neighbourhood.

Police-reported crime, 2025

Per 100,000 peopleSouth RiverdaleCity median
Assault828.7636.3
Robbery69.369.5
Shootings3.210.5
Auto theft217.4192.6
Theft over $5,00088.246.1
Break and enter264.7172.8
Theft from vehicles349.8188.1

Neighbourhood totals from the Toronto Police Service. Rates are per resident, so areas with many visitors and few residents read high.

Something here not right?

Sources

  • Building permits on this lot since 2000: Permits issued or applied for since about 2000, with status.
  • Committee of Adjustment files since 2001: Minor variances and consents (lot splits) on this lot and nearby, with decisions.
  • Development applications: Rezoning, site plan, subdivision and condominium applications.
  • Preliminary zoning reviews: Zoning reviews requested before a permit or variance application.
  • Zoning and overlays: Zoning By-law 569-2013 zone, height, coverage, policy area, parking, rooming house, priority retail street and downtown setback overlays.
  • Lot boundary, street and lane: Lot polygon, its addresses, the street it fronts, corner and public lane contact, with frontage and depth measured from the boundary; City of Toronto land in City use, which is not a home.
  • House and yards: Footprint and roof height of the house and other buildings, and the yard behind the house, from the City's 3D Massing (updated yearly, illustrative).
  • City trees in front of the lot: City-owned trees on the street allowance at this address, with species and trunk diameter. Private trees on the lot are not in open data.
  • Heritage: Heritage Register (listed and designated properties), Official Plan Amendment 720 properties and properties removed from the Register under the 2022 two-year limit.
  • TRCA regulated area: Valleys, floodplains, shorelines and wetlands regulated by the Toronto and Region Conservation Authority.
  • Ravines and natural features: Ravine and Natural Feature Protection area (Chapter 658, map last published 2019), Natural Heritage System and Environmentally Significant Areas.
  • Official Plan policies: Site and Area Specific Policies, Secondary Plans and Major Transit Station Areas covering the lot.
  • Rooming houses, short-term rentals and rental buildings: Multi-tenant house licences, short-term rental registrations and RentSafeTO evaluations at this address.
  • Neighbourhood context: Neighbourhood, 2021 Census figures, police-reported crime rates, schools, parks, TTC stops, cycling routes, serious collisions and traffic counts nearby. Area context only, not a finding about the lot.
  • Orders and by-law investigations: Outstanding Toronto Building orders, and by-law investigations open now or closed in the last two years. Fire and Public Health orders and older closed files are not published.
  • Address points: loaded Nov 22, 2026, published Nov 20, 2026
  • Toronto Building orders: loaded Nov 28, 2026, published Nov 27, 2026
  • Neighbourhood Profiles, 2021 Census: loaded Oct 14, 2026, published Oct 6, 2023
  • Street centrelines: loaded Nov 22, 2026, published Nov 20, 2026
  • City-owned land: loaded Nov 22, 2026, published Nov 16, 2026
  • Committee of Adjustment open applications: loaded Nov 28, 2026, published Nov 27, 2026
  • Committee of Adjustment decisions: loaded Nov 28, 2026, published Nov 27, 2026
  • Committee of Adjustment decisions 2001-2016: loaded Oct 14, 2026, published Feb 20, 2026
  • Collisions with people killed or seriously injured (Toronto Police Service): loaded Nov 22, 2026, published Nov 21, 2026
  • Neighbourhood crime rates (Toronto Police Service): loaded Oct 14, 2026, published Feb 20, 2026
  • Cycling network: loaded Nov 22, 2026, published Nov 16, 2026
  • Development applications: loaded Nov 28, 2026, published Nov 28, 2026
  • Environmentally Significant Areas: loaded Oct 14, 2026, published Mar 16, 2026
  • Green spaces: loaded Nov 15, 2026, published Nov 10, 2026
  • Heritage register: loaded Oct 14, 2026, published Sep 1, 2026
  • Former heritage listings: loaded Oct 14, 2026, published Jul 3, 2025
  • Official Plan Amendment 720 heritage list: loaded Oct 14, 2026, published Sep 1, 2026
  • 3D Massing building footprints: loaded Oct 14, 2026, published Dec 2, 2025
  • By-law investigation addresses: loaded Nov 23, 2026, published Nov 22, 2026
  • By-law investigation deficiencies: loaded Nov 23, 2026, published Nov 22, 2026
  • By-law investigations: loaded Nov 28, 2026, published Nov 27, 2026
  • Major Transit Station Areas: loaded Oct 14, 2026, published Feb 3, 2026
  • Natural Heritage System: loaded Oct 14, 2026, published Mar 16, 2026
  • Neighbourhoods: loaded Oct 14, 2026, published Feb 20, 2026
  • Property boundaries: loaded Nov 27, 2026, published Nov 27, 2026
  • Active building permits: loaded Nov 28, 2026, published Nov 27, 2026
  • Cleared building permits: loaded Nov 28, 2026, published Nov 27, 2026
  • Cleared building permits 2000-2016: loaded Oct 14, 2026, published Jul 8, 2025
  • Preliminary zoning reviews: loaded Nov 28, 2026, published Nov 27, 2026
  • Ravine and natural feature protection: loaded Oct 14, 2026, published Jul 23, 2019
  • RentSafeTO evaluations: loaded Nov 28, 2026, published Nov 27, 2026
  • Multi-tenant house licences: loaded Nov 28, 2026, published Nov 27, 2026
  • Site and Area Specific Policies: loaded Oct 14, 2026, published Mar 16, 2026
  • School locations: loaded Oct 14, 2026, published May 27, 2026
  • Secondary Plans: loaded Oct 14, 2026, published Mar 16, 2026
  • Street trees: loaded Oct 14, 2026, published Jun 4, 2026
  • Short-term rental registrations: loaded Nov 28, 2026, published Nov 27, 2026
  • Traffic counts at intersections: loaded Nov 22, 2026, published Nov 21, 2026
  • TRCA regulation limit: loaded Oct 14, 2026, published Apr 29, 2026
  • TTC stops (GTFS): loaded Nov 8, 2026, published Nov 5, 2026
  • Zoning by-law: loaded Oct 14, 2026, published Feb 20, 2026
  • Lot coverage overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Height overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Parking zone overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Policy area overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Priority retail streets: loaded Oct 14, 2026, published Feb 20, 2026
  • Rooming house overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Zoning setbacks: loaded Oct 14, 2026, published Feb 20, 2026

Contains information licensed under the Open Government Licence – Toronto. TRCA regulation limit © TRCA.

Screening tool based on City of Toronto and TRCA open data. Not a zoning review or legal opinion. Site-specific exceptions, amendments not yet in the open data, minor variances and other by-laws can change the answer. Confirm with a Preliminary Project Review or Zoning Certificate from Toronto Building before buying or designing.

Flag an error

What is not right?

The problem

The records come from the City's open data; we check each flag against them. Your email is used only to answer this.