HousePrecheckCheck an address

465 Huron StToronto · zoning, lot size and permit records

Commercial residential · CR 1.5 (c1.0; r1.0) SS2 (x2378)15.1 × 29.1 m436 m²on Huron St

Not a home

Carpark 205

The City of Toronto's real estate inventory lists Carpark 205 here, on City land in City use. It is not a home for sale, so the house checks and the pre-offer report do not apply.

Looking at a house nearby? What this means for you

  • Transit, rail or parkingGood access, with trains, buses or cars and some noise.
  • 8 development applications open within 300 m, up to 37 storeysNew buildings may go up around here in the next years. More change nearby than at 100% of Toronto houses.
  • Major Transit Station Area: SpadinaThe City plans more homes around the station: good for transit, and more building over time.
N10 m
15.1 m frontage29.1 m deep

Before you offer

From the City's records on this lot. Each item says what it means for a purchase and how to confirm it.

  • 8 development applications open within 300 m

    Good to know

    8 rezoning, site plan, subdivision or condominium applications within 300 m, submitted in the last 10 years, are not closed yet, including buildings of up to 37 storeys. They are listed under Around this lot.

    What it means. New buildings nearby can change views, sunlight, traffic and construction noise for years.

    How to confirm. Each application, its drawings and its status are in the Application Information Centre. Details

    City of Toronto, Development Applications

Not in these records

  • Flooding history. Past basement flooding and insurance claims on this house are not published. Ask the seller directly and ask your insurer before you firm up the offer.
  • Ownership, mortgages and easements. Title is not open data. Your lawyer searches title after the offer; ask for the survey and any easements before.

History of this lot

No permits, applications or Committee of Adjustment files on this lot in the City's open records.

Check before you build

  • Site-specific exception 900.11.10(2378)

    Needs a closer look

    4 older by-laws that still prevail apply to this lot. They can override the standard rules on this page.

    Zoning By-law 569-2013, Chapter 900
Exception 900.11.10(2378)Applies

These parts of the exception apply to this lot's address.

  1. Older by-law A

    Section 12(1) 251 of former City of Toronto By-law 438-86

  2. Older by-law B

    Section 12(2) 132 of former City of Toronto By-law 438-86

  3. Older by-law C

    Section 12(2) 270(a) of former City of Toronto By-law 438-86

  4. Older by-law D

    On 465 Huron St., former City of Toronto by-laws 787-83, 788-83 and 326-85.

By-law 569-2013, Chapter 900

Lot facts

Area
436 m²
Frontage
15.1 m
Depth
29.1 m
Street
Huron St
Corner lot
No
Public lane
None
Max height
14 m
Max lot coverage
—
  • Major Transit Station Area: Spadina. The lot is inside the Spadina Major Transit Station Area approved by the Province (Site and Area Specific Policy 597). Source
  • Downtown Plan Secondary Plan. A Secondary Plan sets more detailed land use, height and density policies for this area. Source
  • Downtown building setback overlay. Towers over 36 m here need extra setbacks above 24 m and 25 m between towers. Houses and other low buildings are not affected. Source
  • Zone CR 1.5 (c1.0; r1.0) SS2 (x2378) (Commercial Residential). Chapter 40, section 40.10 of the by-law. Source

Around this lot

Minor variances approved
90%18 of 20 decisions
Garden suite permits
0
Laneway suite permits
0
Multiplex permits
13
Development applications
27

Within 300 m, last 10 years. 13 suite and multiplex permits: more than at 80% of Toronto houses (median 3). 20 variance decisions: more than at 51% of Toronto houses (median 19).

Recent variance decisions in the same zone

  • Minor varianceRefused

    To permit one 36-storey mixed-use building, which will span across two lots, for a private student residence use. There will be a total of 426 dwelling units, and 220.5 m² of non-residential retail uses (at-grade) within this building. The properties municipally known as 208 Bloor Street West and 210 Bloor Street West are currently under separate ownership and governed by separate Site-Specific Zoning By-laws (By-law 782-2022(OLT), and By-law 778-2024). In the near future, both properties will merge on title under one single entity to facilitate this new development. There is a current Site Plan Control application (No. 21 220574 STE 11 SA) which is currently under review and consideration.

    210 BLOOR ST W · Jul 8, 2026 · 448 m away
  • Minor varianceRefused

    To permit one 36-storey mixed-use building, which will span across two lots, for a private student residence use. There will be a total of 426 dwelling units, and 220.5 m² of non-residential retail uses (at-grade) within this building. The properties municipally known as 208 Bloor Street West and 210 Bloor Street West are currently under separate ownership and governed by separate Site-Specific Zoning By-laws (By-law 782-2022(OLT), and By-law 778-2024). In the near future, both properties will merge on title under one single entity to facilitate this new development. There is a current Site Plan Control application (No. 21 220574 STE 11 SA) which is currently under review and consideration.

    208 BLOOR ST W · Jul 8, 2026 · 461 m away
  • Minor varianceApproved

    To convert the existing two-and-one-half-storey commercial building (eating establishment) into a mixed-use building by constructing a rear five-storey addition. This altered building will contain one non-residential unit (including one bar/pub, and five office spaces), one residential dwelling unit (to be located on the fifth storey), side (west) third and fourth storey terraces, a side (east) fifth storey terraces, a rear parking pad (for one visitor parking space and one accessible parking space), and a rear yard ancillary building (waste and recyclable material storage shed). This existing building is a heritage building.

    36 PRINCE ARTHUR AVE · Jul 23, 2025 · 391 m away
  • Minor varianceApproved

    To alter the development standards (as approved under Site Specific Zoning By-law 595-2021(OLT), as amended by City Wide By-law 569-2013), for a new mixed-use building.

    316 BLOOR ST W · Dec 13, 2023 · 159 m away
  • Minor varianceRefused

    To alter the development standards, as approved within Site Specific Zoning By-law 73-2021, which include changes to the overall tower height (29-storeys to 34-storeys) and a reduction of indoor amenity space.

    478 HURON ST · Nov 8, 2023 · 48 m away

Latest activity nearby

  • Building permit

    Proposed modification to existing standpipe system related to permit application # 26-15221 BLD 00 BA.

    252 BLOOR ST W · Nov 17, 2026 · 236 m away
  • Building permitmultiplex

    Proposal for HVAC upgrade, replacement of hydronic heating system, ameliorated ventilation

    482 HURON ST · Nov 10, 2026 · 54 m away
  • Building permitmultiplex

    Proposal for HVAC upgrade, replacement of hydronic heating system, ameliorated ventilation

    480 HURON ST · Nov 10, 2026 · 52 m away
  • Building permit

    HVAC upgrade, replacement of hydronic heating system, ameliorated ventilation

    492 HURON ST · Nov 5, 2026 · 80 m away
  • Building permit

    REPAIRS TO EXISITING REAR SECOND FLOOR DECK

    23 MADISON AVE · Nov 5, 2026 · 114 m away
  • Building permit

    Proposal to replace existing roof mounted life-safety natural gas emergency generator with a new outdoor life-safety natural gas generator.

    341 BLOOR ST W · Nov 4, 2026 · 125 m away
  • Building permit

    Repairs to existing rear second floor deck

    27 MADISON AVE · Nov 4, 2026 · 122 m away
  • Building permit

    Proposal for Installation of roof edge railings, roof mounted stair and ladder ports at TTC's St. George Station -St. George Entrance

    139 ST GEORGE ST · Oct 29, 2026 · 142 m away
  • Building permit

    Proposal for installation of roof edge railings, roof mounted stair, fixed ladder and ladder port at TTC's Spadina Stn -Main Entrance

    7 SPADINA RD · Oct 28, 2026 · 194 m away
  • Building permit

    Interior alterations to include a new in-suite laundry and renovation of 2 bathrooms and kitchen. All new fixtures and new laundry to tie into existing rough-in plumbing locations.

    190 ST GEORGE ST · Oct 14, 2026 · 164 m away

Neighbourhood: Annex

About the area around the lot, not the lot itself.

Nearest station
St George Station2 min walk
Nearest TTC stop
St George Station - Westbound Platform2 min walk
Nearest cycling route
Prince Arthur AveSigned Route (No Pavement Markings), 1 min walk
Nearest traffic count
2,401 vehicles in 8 hPrince Arthur Ave / Huron St, 60 m away, May 5, 2005
Serious collisions within 500 m
32021–2026, killed or seriously injured: 0 fatal, 0 with pedestrians, 2 with cyclists
Parks
Huron Street Playground2 min walk
Paul Martel Park2 min walk
Huron - Washington Parkette3 min walk

Schools within 1 km

  • HOWLETT ACADEMY SCHOOL Private 2 min walk
  • UNIVERSITY OF TORONTO SCHOOLS Private 3 min walk
  • SCHOOL OF CONTINUING STUDIES - U OF T, BLDG 103 University 3 min walk
  • TADDLE CREEK MONTESSORI SCHOOL Private 4 min walk
  • MUNK SCHOOL OF GLOBAL AFFAIRS AT THE OBSERVATORY - U OF T, BLDG 89 University 4 min walk
  • PAUL PENNA DOWNTOWN JEWISH DAY SCHOOL & MILES NADAL JEWISH COMMUNITY CENTRE Private 5 min walk

Being near a school does not mean the lot is in its catchment; check with the board.

2021 Census

FigureAnnexMedian neighbourhood
Median household income (2020)$85,000$84,500
Households that own their home41%54%
Population (2021)29,30016,813
Homes built in 1960 or before40%29%
Homes needing major repairs6%7%

Statistics Canada 2021 Census, 25% sample, by City of Toronto neighbourhood.

Police-reported crime, 2025

Per 100,000 peopleAnnexCity median
Assault1080.9636.3
Robbery80.569.5
Homicide5.25.3
Shootings5.210.5
Auto theft116.9192.6
Theft over $5,000114.346.1
Break and enter387.1172.8
Theft from vehicles220.9188.1

Neighbourhood totals from the Toronto Police Service. Rates are per resident, so areas with many visitors and few residents read high.

Something here not right?

Sources

  • Building permits on this lot since 2000: Permits issued or applied for since about 2000, with status.
  • Committee of Adjustment files since 2001: Minor variances and consents (lot splits) on this lot and nearby, with decisions.
  • Development applications: Rezoning, site plan, subdivision and condominium applications.
  • Preliminary zoning reviews: Zoning reviews requested before a permit or variance application.
  • Zoning and overlays: Zoning By-law 569-2013 zone, height, coverage, policy area, parking, rooming house, priority retail street and downtown setback overlays.
  • Lot boundary, street and lane: Lot polygon, its addresses, the street it fronts, corner and public lane contact, with frontage and depth measured from the boundary; City of Toronto land in City use, which is not a home.
  • House and yards: Footprint and roof height of the house and other buildings, and the yard behind the house, from the City's 3D Massing (updated yearly, illustrative).
  • City trees in front of the lot: City-owned trees on the street allowance at this address, with species and trunk diameter. Private trees on the lot are not in open data.
  • Heritage: Heritage Register (listed and designated properties), Official Plan Amendment 720 properties and properties removed from the Register under the 2022 two-year limit.
  • TRCA regulated area: Valleys, floodplains, shorelines and wetlands regulated by the Toronto and Region Conservation Authority.
  • Ravines and natural features: Ravine and Natural Feature Protection area (Chapter 658, map last published 2019), Natural Heritage System and Environmentally Significant Areas.
  • Official Plan policies: Site and Area Specific Policies, Secondary Plans and Major Transit Station Areas covering the lot.
  • Rooming houses, short-term rentals and rental buildings: Multi-tenant house licences, short-term rental registrations and RentSafeTO evaluations at this address.
  • Neighbourhood context: Neighbourhood, 2021 Census figures, police-reported crime rates, schools, parks, TTC stops, cycling routes, serious collisions and traffic counts nearby. Area context only, not a finding about the lot.
  • Orders and by-law investigations: Outstanding Toronto Building orders, and by-law investigations open now or closed in the last two years. Fire and Public Health orders and older closed files are not published.
  • Address points: loaded Nov 22, 2026, published Nov 20, 2026
  • Toronto Building orders: loaded Nov 27, 2026, published Nov 26, 2026
  • Neighbourhood Profiles, 2021 Census: loaded Oct 14, 2026, published Oct 6, 2023
  • Street centrelines: loaded Nov 22, 2026, published Nov 20, 2026
  • City-owned land: loaded Nov 22, 2026, published Nov 16, 2026
  • Committee of Adjustment open applications: loaded Nov 27, 2026, published Nov 26, 2026
  • Committee of Adjustment decisions: loaded Nov 27, 2026, published Nov 26, 2026
  • Committee of Adjustment decisions 2001-2016: loaded Oct 14, 2026, published Feb 20, 2026
  • Collisions with people killed or seriously injured (Toronto Police Service): loaded Nov 22, 2026, published Nov 21, 2026
  • Neighbourhood crime rates (Toronto Police Service): loaded Oct 14, 2026, published Feb 20, 2026
  • Cycling network: loaded Nov 22, 2026, published Nov 16, 2026
  • Development applications: loaded Nov 27, 2026, published Nov 27, 2026
  • Environmentally Significant Areas: loaded Oct 14, 2026, published Mar 16, 2026
  • Green spaces: loaded Nov 15, 2026, published Nov 10, 2026
  • Heritage register: loaded Oct 14, 2026, published Sep 1, 2026
  • Former heritage listings: loaded Oct 14, 2026, published Jul 3, 2025
  • Official Plan Amendment 720 heritage list: loaded Oct 14, 2026, published Sep 1, 2026
  • 3D Massing building footprints: loaded Oct 14, 2026, published Dec 2, 2025
  • By-law investigation addresses: loaded Nov 23, 2026, published Nov 22, 2026
  • By-law investigation deficiencies: loaded Nov 23, 2026, published Nov 22, 2026
  • By-law investigations: loaded Nov 27, 2026, published Nov 26, 2026
  • Major Transit Station Areas: loaded Oct 14, 2026, published Feb 3, 2026
  • Natural Heritage System: loaded Oct 14, 2026, published Mar 16, 2026
  • Neighbourhoods: loaded Oct 14, 2026, published Feb 20, 2026
  • Property boundaries: loaded Nov 27, 2026, published Nov 27, 2026
  • Active building permits: loaded Nov 27, 2026, published Nov 26, 2026
  • Cleared building permits: loaded Nov 27, 2026, published Nov 26, 2026
  • Cleared building permits 2000-2016: loaded Oct 14, 2026, published Jul 8, 2025
  • Preliminary zoning reviews: loaded Nov 27, 2026, published Nov 26, 2026
  • Ravine and natural feature protection: loaded Oct 14, 2026, published Jul 23, 2019
  • RentSafeTO evaluations: loaded Nov 27, 2026, published Nov 26, 2026
  • Multi-tenant house licences: loaded Nov 27, 2026, published Nov 26, 2026
  • Site and Area Specific Policies: loaded Oct 14, 2026, published Mar 16, 2026
  • School locations: loaded Oct 14, 2026, published May 27, 2026
  • Secondary Plans: loaded Oct 14, 2026, published Mar 16, 2026
  • Street trees: loaded Oct 14, 2026, published Jun 4, 2026
  • Short-term rental registrations: loaded Nov 27, 2026, published Nov 26, 2026
  • Traffic counts at intersections: loaded Nov 22, 2026, published Nov 21, 2026
  • TRCA regulation limit: loaded Oct 14, 2026, published Apr 29, 2026
  • TTC stops (GTFS): loaded Nov 8, 2026, published Nov 5, 2026
  • Zoning by-law: loaded Oct 14, 2026, published Feb 20, 2026
  • Lot coverage overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Height overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Parking zone overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Policy area overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Priority retail streets: loaded Oct 14, 2026, published Feb 20, 2026
  • Rooming house overlay: loaded Oct 14, 2026, published Feb 20, 2026
  • Zoning setbacks: loaded Oct 14, 2026, published Feb 20, 2026

Contains information licensed under the Open Government Licence – Toronto. TRCA regulation limit © TRCA.

Screening tool based on City of Toronto and TRCA open data. Not a zoning review or legal opinion. Site-specific exceptions, amendments not yet in the open data, minor variances and other by-laws can change the answer. Confirm with a Preliminary Project Review or Zoning Certificate from Toronto Building before buying or designing.

Flag an error

What is not right?

The problem

The records come from the City's open data; we check each flag against them. Your email is used only to answer this.