HousePrecheckCheck an address

2 Hoskin AveToronto · zoning, lot size and permit records

≈ 39.9 × 217.1 m6,148 m²on Hoskin Ave

Not a home

Land without a building

The City's 3D model of buildings shows nothing standing on this parcel: vacant land, a parking lot or a yard. It is not a home for sale, so the house checks and the pre-offer report do not apply.

Looking at a house nearby? What this means for you

  • Empty land or parkingWhat gets built here matters most to the street: read the applications on it and around it below.
  • 2 development applications open within 300 m, up to 9 storeysNew buildings may go up around here in the next years. More change nearby than at 91% of Toronto houses.
N50 m
≈ 39.9 m frontage≈ 217.1 m deepirregular lot, estimated

Before you offer

From the City's records on this lot. Each item says what it means for a purchase and how to confirm it.

  • 2 development applications open within 300 m

    Good to know

    2 rezoning, site plan, subdivision or condominium applications within 300 m, submitted in the last 10 years, are not closed yet, including buildings of up to 9 storeys. They are listed under Around this lot.

    What it means. New buildings nearby can change views, sunlight, traffic and construction noise for years.

    How to confirm. Each application, its drawings and its status are in the Application Information Centre. Details

    City of Toronto, Development Applications

Not in these records

  • Flooding history. Past basement flooding and insurance claims on this house are not published. Ask the seller directly and ask your insurer before you firm up the offer.
  • Ownership, mortgages and easements. Title is not open data. Your lawyer searches title after the offer; ask for the survey and any easements before.

History of this lot

No permits, applications or Committee of Adjustment files on this lot in the City's open records.

Check before you build

  • Zoning not in By-law 569-2013

    Needs a closer look

    This lot is not covered by the citywide zoning by-law's map. It is probably still governed by a former municipal by-law, which this tool does not read yet.

    Zoning By-law 569-2013

Lot facts

Area
6,148 m²
Frontage
39.9 mestimated, irregular lot
Depth
217.1 mestimated, irregular lot
Street
Hoskin Ave
Corner lot
No
Public lane
None
Max height
—
Max lot coverage
—

    Around this lot

    Minor variances approved
    100%2 of 2 decisions
    Garden suite permits
    0
    Laneway suite permits
    0
    Multiplex permits
    0
    Development applications
    7

    Within 300 m, last 10 years. 0 suite and multiplex permits: no more than at most Toronto houses (median 3). 2 variance decisions: no more than at most Toronto houses (median 19).

    Recent variance decisions in the same zone

    • Minor varianceRefused

      To permit one 36-storey mixed-use building, which will span across two lots, for a private student residence use. There will be a total of 426 dwelling units, and 220.5 m² of non-residential retail uses (at-grade) within this building. The properties municipally known as 208 Bloor Street West and 210 Bloor Street West are currently under separate ownership and governed by separate Site-Specific Zoning By-laws (By-law 782-2022(OLT), and By-law 778-2024). In the near future, both properties will merge on title under one single entity to facilitate this new development. There is a current Site Plan Control application (No. 21 220574 STE 11 SA) which is currently under review and consideration.

      210 BLOOR ST W · Jul 8, 2026 · 313 m away
    • Minor varianceRefused

      To permit one 36-storey mixed-use building, which will span across two lots, for a private student residence use. There will be a total of 426 dwelling units, and 220.5 m² of non-residential retail uses (at-grade) within this building. The properties municipally known as 208 Bloor Street West and 210 Bloor Street West are currently under separate ownership and governed by separate Site-Specific Zoning By-laws (By-law 782-2022(OLT), and By-law 778-2024). In the near future, both properties will merge on title under one single entity to facilitate this new development. There is a current Site Plan Control application (No. 21 220574 STE 11 SA) which is currently under review and consideration.

      208 BLOOR ST W · Jul 8, 2026 · 314 m away
    • Minor varianceApproved

      To alter the existing three-storey detached commercial building by constructing rear fourth, fifth, and sixth storey additions, with a green roof. There will be office spaces on each level of this building.

      8 PRINCE ARTHUR AVE · Mar 11, 2026 · 461 m away
    • Minor varianceApproved

      To convert the existing two-storey detached main dwelling into a mixed-use building through interior alterations to permit a restaurant (café) use within the ground floor of the building. Also, to construct a new two-storey detached ancillary building (containing one laneway suite with bedrooms within the basement below) in the rear yard, abutting the Public laneway. There will be a total of two residential dwelling units on this lot (one in the main dwelling and one in the laneway suite).

      356 HURON ST · Dec 10, 2025 · 494 m away
    • Minor varianceApproved

      To convert the existing two-and-one-half-storey commercial building (eating establishment) into a mixed-use building by constructing a rear five-storey addition. This altered building will contain one non-residential unit (including one bar/pub, and five office spaces), one residential dwelling unit (to be located on the fifth storey), side (west) third and fourth storey terraces, a side (east) fifth storey terraces, a rear parking pad (for one visitor parking space and one accessible parking space), and a rear yard ancillary building (waste and recyclable material storage shed). This existing building is a heritage building.

      36 PRINCE ARTHUR AVE · Jul 23, 2025 · 446 m away

    Latest activity nearby

    • Building permit

      Repairs to the existing 8th Floor Pool Deck and 8th Floor Men's Locker Room, including: waterproofing repairs, structural concrete repairs, interior finish repairs.

      220 BLOOR ST W · Nov 20, 2026 · 299 m away
    • Building permit

      A proposal to erect and display 2 ground signs, one wall sign and one overhanging structure sign, all displaying static copy.***ROYAL ONTARIO MUSEUM***

      100 QUEEN'S PARK · Nov 10, 2026 · 220 m away
    • Building permit

      Replace existing roof mounted exhaust fans (EF-2.1,29,30), Replace existing pumps, CP-5 and CP-6 found in mechanical room E045, Replace existing pump, CP-11 and CP-14 found in mechanical room 55, Replace existing pump, M-42 found in mechanical room 55, Replace the existing air handling units, AHU-311 and AHU-319 within 3rd floor mechanical rooms in 311 and 319.

      80 QUEEN'S PARK · Nov 4, 2026 · 78 m away
    • Building permit

      Proposed interior alterations on the third floor in the area of rooms 318, 320, 322, 323, 324, and 325 and related electrical work.

      80 QUEEN'S PARK · Oct 15, 2026 · 78 m away
    • Building permit

      Proposed wholesale removal and replacement of existing conventional BUR roof with a new two-ply cold-adhered conventional modified bitumen membrane assembly, wholesale replacement of parapet metal flashing, localized masonry repairs and mortar repointing as directed by the consultant, wholesale removal and replacement of the existing deteriorated roof deck and joists

      7 HART HOUSE CRCL · Oct 8, 2026 · 249 m away
    • Building permit

      Proposal for fire alarm system panel repair. Edwards EST3 to EST4

      111 QUEEN'S PARK · Sep 30, 2026 · 290 m away
    • Zoning review

      Closed

      6 HOSKIN AVE · Aug 28, 2026 · 99 m away
    • Zoning review

      Notice Sent

      90 DEVONSHIRE PL · Aug 4, 2026 · 254 m away
    • Building permit

      To renovate the interior central atrium space of the ROM. Scope includes new skylight, feature stair, gallery wall openings, and new level raised floor.

      100 QUEEN'S PARK · May 25, 2026 · 220 m away
    • Building permit

      Alternative Solution for 65 mm Diameter Standpipe Hose Connections Serving Basement

      7 HART HOUSE CRCL · May 22, 2026 · 249 m away

    Neighbourhood: University

    About the area around the lot, not the lot itself.

    Nearest station
    Museum Station3 min walk
    Nearest TTC stop
    Queen's Park Cres West at Hoskin Ave2 min walk
    Nearest cycling route
    Hoskin AveCycle Track, 2 min walk
    Nearest traffic count
    13,187 vehicles in 14 hQueen's Park Cres W / Hoskin Ave / Queen's Park Trl, 140 m away, Jun 25, 2025
    Serious collisions within 500 m
    82021–2026, killed or seriously injured: 2 fatal, 3 with pedestrians, 4 with cyclists
    Parks
    Queen's Park2 min walk
    Bloor - Bedford Parkette5 min walk
    Village of Yorkville Park8 min walk

    Schools within 1 km

    • MUNK SCHOOL OF GLOBAL AFFAIRS GRAHAM LIBRARY - U OF T, BLDG 12C University 3 min walk
    • MUNK SCHOOL OF GLOBAL AFFAIRS AT TRINITY - U OF T, BLDG 12A University 3 min walk
    • ROTMAN SCHOOL OF MANAGEMENT - U OF T, BLDG 134 University 5 min walk
    • MUNK SCHOOL OF GLOBAL AFFAIRS AT THE OBSERVATORY - U OF T, BLDG 89 University 5 min walk
    • TORONTO SCHOOL OF THEOLOGY - U OF T, BLDG 434 University 6 min walk
    • ROSEDALE DAY SCHOOL Private 6 min walk

    Being near a school does not mean the lot is in its catchment; check with the board.

    2021 Census

    FigureUniversityMedian neighbourhood
    Median household income (2020)$80,000$84,500
    Households that own their home39%54%
    Population (2021)6,43516,813
    Homes built in 1960 or before59%29%
    Homes needing major repairs11%7%

    Statistics Canada 2021 Census, 25% sample, by City of Toronto neighbourhood.

    Police-reported crime, 2025

    Per 100,000 peopleUniversityCity median
    Assault1740.5636.3
    Robbery133.969.5
    Homicide12.25.3
    Auto theft182.6192.6
    Theft over $5,000121.746.1
    Break and enter730.3172.8
    Theft from vehicles353188.1

    Neighbourhood totals from the Toronto Police Service. Rates are per resident, so areas with many visitors and few residents read high.

    Something here not right?

    Sources

    • Building permits on this lot since 2000: Permits issued or applied for since about 2000, with status.
    • Committee of Adjustment files since 2001: Minor variances and consents (lot splits) on this lot and nearby, with decisions.
    • Development applications: Rezoning, site plan, subdivision and condominium applications.
    • Preliminary zoning reviews: Zoning reviews requested before a permit or variance application.
    • Zoning and overlays: Zoning By-law 569-2013 zone, height, coverage, policy area, parking, rooming house, priority retail street and downtown setback overlays.
    • Lot boundary, street and lane: Lot polygon, its addresses, the street it fronts, corner and public lane contact, with frontage and depth measured from the boundary; City of Toronto land in City use, which is not a home.
    • House and yards: Footprint and roof height of the house and other buildings, and the yard behind the house, from the City's 3D Massing (updated yearly, illustrative).
    • City trees in front of the lot: City-owned trees on the street allowance at this address, with species and trunk diameter. Private trees on the lot are not in open data.
    • Heritage: Heritage Register (listed and designated properties), Official Plan Amendment 720 properties and properties removed from the Register under the 2022 two-year limit.
    • TRCA regulated area: Valleys, floodplains, shorelines and wetlands regulated by the Toronto and Region Conservation Authority.
    • Ravines and natural features: Ravine and Natural Feature Protection area (Chapter 658, map last published 2019), Natural Heritage System and Environmentally Significant Areas.
    • Official Plan policies: Site and Area Specific Policies, Secondary Plans and Major Transit Station Areas covering the lot.
    • Rooming houses, short-term rentals and rental buildings: Multi-tenant house licences, short-term rental registrations and RentSafeTO evaluations at this address.
    • Neighbourhood context: Neighbourhood, 2021 Census figures, police-reported crime rates, schools, parks, TTC stops, cycling routes, serious collisions and traffic counts nearby. Area context only, not a finding about the lot.
    • Orders and by-law investigations: Outstanding Toronto Building orders, and by-law investigations open now or closed in the last two years. Fire and Public Health orders and older closed files are not published.
    • Address points: loaded Nov 22, 2026, published Nov 20, 2026
    • Toronto Building orders: loaded Nov 27, 2026, published Nov 26, 2026
    • Neighbourhood Profiles, 2021 Census: loaded Oct 14, 2026, published Oct 6, 2023
    • Street centrelines: loaded Nov 22, 2026, published Nov 20, 2026
    • City-owned land: loaded Nov 22, 2026, published Nov 16, 2026
    • Committee of Adjustment open applications: loaded Nov 27, 2026, published Nov 26, 2026
    • Committee of Adjustment decisions: loaded Nov 27, 2026, published Nov 26, 2026
    • Committee of Adjustment decisions 2001-2016: loaded Oct 14, 2026, published Feb 20, 2026
    • Collisions with people killed or seriously injured (Toronto Police Service): loaded Nov 22, 2026, published Nov 21, 2026
    • Neighbourhood crime rates (Toronto Police Service): loaded Oct 14, 2026, published Feb 20, 2026
    • Cycling network: loaded Nov 22, 2026, published Nov 16, 2026
    • Development applications: loaded Nov 27, 2026, published Nov 27, 2026
    • Environmentally Significant Areas: loaded Oct 14, 2026, published Mar 16, 2026
    • Green spaces: loaded Nov 15, 2026, published Nov 10, 2026
    • Heritage register: loaded Oct 14, 2026, published Sep 1, 2026
    • Former heritage listings: loaded Oct 14, 2026, published Jul 3, 2025
    • Official Plan Amendment 720 heritage list: loaded Oct 14, 2026, published Sep 1, 2026
    • 3D Massing building footprints: loaded Oct 14, 2026, published Dec 2, 2025
    • By-law investigation addresses: loaded Nov 23, 2026, published Nov 22, 2026
    • By-law investigation deficiencies: loaded Nov 23, 2026, published Nov 22, 2026
    • By-law investigations: loaded Nov 27, 2026, published Nov 26, 2026
    • Major Transit Station Areas: loaded Oct 14, 2026, published Feb 3, 2026
    • Natural Heritage System: loaded Oct 14, 2026, published Mar 16, 2026
    • Neighbourhoods: loaded Oct 14, 2026, published Feb 20, 2026
    • Property boundaries: loaded Nov 27, 2026, published Nov 27, 2026
    • Active building permits: loaded Nov 27, 2026, published Nov 26, 2026
    • Cleared building permits: loaded Nov 27, 2026, published Nov 26, 2026
    • Cleared building permits 2000-2016: loaded Oct 14, 2026, published Jul 8, 2025
    • Preliminary zoning reviews: loaded Nov 27, 2026, published Nov 26, 2026
    • Ravine and natural feature protection: loaded Oct 14, 2026, published Jul 23, 2019
    • RentSafeTO evaluations: loaded Nov 27, 2026, published Nov 26, 2026
    • Multi-tenant house licences: loaded Nov 27, 2026, published Nov 26, 2026
    • Site and Area Specific Policies: loaded Oct 14, 2026, published Mar 16, 2026
    • School locations: loaded Oct 14, 2026, published May 27, 2026
    • Secondary Plans: loaded Oct 14, 2026, published Mar 16, 2026
    • Street trees: loaded Oct 14, 2026, published Jun 4, 2026
    • Short-term rental registrations: loaded Nov 27, 2026, published Nov 26, 2026
    • Traffic counts at intersections: loaded Nov 22, 2026, published Nov 21, 2026
    • TRCA regulation limit: loaded Oct 14, 2026, published Apr 29, 2026
    • TTC stops (GTFS): loaded Nov 8, 2026, published Nov 5, 2026
    • Zoning by-law: loaded Oct 14, 2026, published Feb 20, 2026
    • Lot coverage overlay: loaded Oct 14, 2026, published Feb 20, 2026
    • Height overlay: loaded Oct 14, 2026, published Feb 20, 2026
    • Parking zone overlay: loaded Oct 14, 2026, published Feb 20, 2026
    • Policy area overlay: loaded Oct 14, 2026, published Feb 20, 2026
    • Priority retail streets: loaded Oct 14, 2026, published Feb 20, 2026
    • Rooming house overlay: loaded Oct 14, 2026, published Feb 20, 2026
    • Zoning setbacks: loaded Oct 14, 2026, published Feb 20, 2026

    Contains information licensed under the Open Government Licence – Toronto. TRCA regulation limit © TRCA.

    Screening tool based on City of Toronto and TRCA open data. Not a zoning review or legal opinion. Site-specific exceptions, amendments not yet in the open data, minor variances and other by-laws can change the answer. Confirm with a Preliminary Project Review or Zoning Certificate from Toronto Building before buying or designing.

    Flag an error

    What is not right?

    The problem

    The records come from the City's open data; we check each flag against them. Your email is used only to answer this.